Program 4: Calendars and working time
Part 4 of the Program series. Set a construction programme calendar: public holidays, half days, recurring weekly rules and a six day working week per activity, and see the finish date move. Everything shown can also be done by asking the Map Metra connector in Claude or ChatGPT.
How to
- 1
The calendar
Choose Calendar on the toolbar. Weekends are shaded as non-working days.
- 2
Public holidays
Click a date to set its working hours. Zero hours makes it a non-working day, and the note says why.
- 3
Unusual hours
A day can also have unusual hours. Christmas Eve becomes a half day, with four hours of work.
- 4
Recurring rules
The letters under Recurring set a rule for every week. Here, every Friday is cut to six hours, and the finish moves to the sixteenth of February.
- 5
Working week
Each activity can also follow its own working week, in the Working week column. Put the external walls on a six day week, so the bricklayers work Saturdays.