Civil quantities follow an alignment. Chainage gives every point a distance along it, and comparing existing ground with design levels gives the cut and fill.

How to

  1. 1

    Set out the chainage

    Trace the road or pipe alignment on the plan so every point along it has a chainage, its distance from the start.

  2. 2

    Enter the levels

    Read existing ground and design levels at each chainage from the long section or plan.

  3. 3

    Calculate cut and fill

    Map Metra compares existing and design levels along the alignment and gives cut and fill volumes.

  4. 4

    Carry to the BOQ

    Earthworks volumes flow into the Bill of Quantities with the rest of the takeoff, ready to price.